Meeting to gauge support for a Shed | 8th March 2010 |
Opening of first shed | 14th June 2010 |
Opening of addition to shed | 20th May 2011 |
Air conditioning of two sheds | Sept 2011 |
Shed 3 for kitchen/meeting | Jan 2012 |
Shed 4 for Metalwork & Painting | Jan 2012 |
Hard stand completed | Feb 2012 |
20’ Sea container for storage | April 2012 |
Cyclone Dust extraction system | Feb 2014 |
In under 4 years we have gone from an unlined garage to four sheds, two of which are lined and air conditioned, and an outdoor hard stand.
The interiors have also been developed with underfloor and overhead ducting for dust removal which has just been upgraded to accommodate a new cyclone system. We have completed two new workbenches with 4 vices.
This just shows what men with a can do attitude can achieve given a bit of encouragement.